Notices and Tasks for the Current Funding Year:
FY2018 (7/1/18-6/30/19)
E-Rate Step 5: Bill Payment
  • FY2018File a Form 486 in EPC to indicate the start of FY2018 services
  •  
    Resource: UPDATED[PDF]FY2018 Form 486 How to Guide
    Constraints: cannot be filed until an FCDL has been issued
    Deadline: October 29, 2018 if FCDL is dated July 1, 2018 or earlier
    or
    120 days from date of FCDL if dated after July 1, 2018
E-Rate Step 6: Filing for a Refund
  • FY2018File a Form 498 in EPC in preparation for receiving FY2017 reimbursements via direct deposit
     Note: a new form is not required for FY2018 if you previously filed one and have an approved 498 ID
  •  
    Resource: [PDF]Form 498 How to Guide
    Constraints: you cannot file a BEAR form for FY2018 until you have an approved 498ID
    Deadline: before first FY2018 BEAR
  • FY2018File BEARs for reimbursements for FY2018 products and services
  •  
    Resource: [PDF]Form 472 BEAR How to Guide
    Constraints: cannot be filed until a Form 486 is filed and you have an approved 498 ID
    Deadline: October 28, 2019

Notices and Tasks for the Next Funding Year:
FY2019 (7/1/19-6/30/20)
 
E-Rate Step 1: Making a Plan
  • FY2019File a Form 470 in EPC to identify desired products and services
  •  
    Resource: UPDATED[PDF]FY2019 Form 470 How to Guide
    Deadline: February 27, 2019 is the last day to post a Form 470 in EPC or attach an RFP
  • FY2019Next steps after filing the Form 470
  • FY2019Form 470 Wrap-Up Step 1: Selecting Vendors
  •  
    Constraints: before selecting a vendor, you must wait at least 28 days after the date the Form 470 is filed and the date the RFP is issued, whichever is later
  • FY2019Form 470 Wrap-Up Step 2: Signing Contracts
  •  
    Constraints: before signing a contract, you must wait at least 28 days after the date the Form 470 is filed and the date the RFP is issued, whichever is later
Networkmaine Members only: Pre-Enrollment
  • FY2019Pre-Enrollment   for Networkmaine sites wihout DOE reported NSLP data
  •  
    Window: October 22, 2018 - November 9, 2018
E-Rate Step 3: Applying for Funding
  • FY2019Update your EPC Profile during the Administrative Window
  •  
    Resource: UPDATED[PDF]Update Your EPC Profile
    Constraints: The Administrative Window is a designated timeframe during which applicants can update their EPC profiles for the next funding year. Profile data will be locked down after the window closes and cannot be changed.
    Window: October 1, 2018 - January 15, 2019 (profiles will be locked at 11:59 PM EST)s
  • FY2019File a Form 471 in EPC to request E-Rate funding
  •  
    Resource: EPC Guides for Form 471 Prep and Filing Forms for C1 and C2
    Constraints: cannot be filed until 29 days after Form 470 is filed
    Window: January 16, 2019 (12:00 Noon EST) - March 27, 2019 (11:59 PM EDT)
Networkmaine Members only: Enrollment
  • FY2019Enrollment   for all Networkmaine sites (school districts, independent schools, libraries)
  •  
    Window: January 14, 2019 - January 25, 2019
E-Rate Step 4: Funding Approval